This week in focus: Delivery of 60MVA, 132/33kV power transformer and accessories to Ojo Transmission Substation to cater for supplies to Ajangbadi, Ojo, Festac Town, Satellite Town, Iba, Iyana-Iba, Ijegun, etc.
This is a follow-up to the deliveries at Amukpe Transmission Substation in Delta State that will benefit consumers in Sapele, Industrial, Adoje, Mosogar, Abraka, etc.
A third set of deliveries were made at Okene In Kogi State earlier in the week.
When fully commissioned, a total of 180MVA transmission capacity will be added to the national grid system at critical transmission-distribution interfaces.
Potiskum, Omuaran, Maryland and Ihovbor Transmission Substations to follow.